North Bridge Sailing Club
Completed with Minimal Access
Completion Time
3 days
ANOTHER ONE OF LIDORAN'S RECENT PROJECTS!
The pathway shown was the only access we had to get to the Sailing Clubs Shed.
Most materials were dropped off to the foreshore by barge; all other materials including flashings, tools & ladders were hand carried on the pathway to & from the shed.
Five boys stripped the asbestos roof & timber wall cladding on the first day of arrival, leaving another 3 days for 3 boys to replace the walls & roof with Colorbond.