Donaldson Australasia Pty Ltd

Lucca Rd

  • LOCATION

    Wyong, NSW

  • Roofing Replaced

    6,000 ㎡

  • Completion Time

    7 days

As usual Lidoran had many shut down jobs over the Christmas & New Year break. One of these projects was Donaldson's on the Central Coast of NSW a 6,000m2 asbestos re-roof.

Although the Central Coast is a holiday destination, it was no holiday for the Lidoran crew. Before works could commence every item of stock, machinery & equipment had to be covered & wrapped; our professional preparation team of workers carried out these works.

We then had 8 days for the roofing crew to remove & replace the roof including box gutters, wire mesh & insulation. The weather took its toll with some really hot days followed by thunderstorms. However the crew pushed on making up lost time with some long days. We reached our target with a day up our sleeve.

Once again the Lidoran Team delivered on time.